VDC · Phase Tracker
VDC Coordination Field Reference

A coordination system built around the physics of a building.

Most coordination tools track clashes. This one tracks the conditions that make clashes inevitable — and the sequence of decisions that prevents them.

Two-phase model Constraint hierarchy Gravity drainage logic Trade accountability Weekly commit cycle Navisworks integration

What the VDC Phase Tracker does

It manages the pre-construction BIM coordination process from kickoff through fabrication release — organized around areas of the building, the disciplines working in each one, and the specific constraints that must be resolved in the right sequence.

A coordination project is a series of interdependent decisions. The wrong decision made first forces every decision that follows to work around it. The right sequence — defined by the physics of the building, not by schedule convenience — is what this tool enforces.

The tracker holds the complete coordination state of the project: which systems are defined, which trades are responsible for them, which areas of the building require coordination, what constraints exist in each area, what state those constraints are in, and who committed to what in each week's coordination cycle. That information is stored in a single .vdcpt file that travels with the project, can be shared, archived, and opened by any team member.

The problem it solves
Coordination that starts too early

When trades begin resolving clashes before all discipline models are loaded, they are solving problems against an incomplete picture. Solutions become provisional. When the missing elements arrive, every resolved clash must be re-checked. The cost is not just time — it is the erosion of team trust in the coordination process itself.

The mechanism
A loading gate before every area

No area can enter coordination until every expected discipline has confirmed their elements are loaded at the required level of development, a five-point checklist is satisfied, and the VDC manager has signed off. The gate is structural — not a suggestion. Coordination that starts before it passes is flagged as premature and scored accordingly.

The hierarchy
Physics before preference

Gravity drainage, structural clearances, and existing conditions are not negotiable. They constrain everything that follows. The tier system encodes this reality — T0 and T1A constraints must be resolved before T3 coordination can produce reliable solutions. Resolving in the wrong order produces solutions that look right until the element they ignored shows up.

The record
Weekly commits, not meeting minutes

Every week's trade commitments are logged against specific constraints and attributed to specific contacts. At end of week, the VDC manager commits the week — freezing a permanent snapshot that can be saved as its own file. The report emails directly from the commit, listing every trade's resolved, activated, and pending items with contact names.

Every area has two distinct phases

Loading and coordination are different activities with different completion criteria. They must be kept separate. Mixing them is the most common source of rework in pre-construction coordination.

Area example Main mechanical room threshold
Loading phase
Coordination phase
Week 2 — all disciplines submit Week 4 — gate passed, coordination begins Week 8 — complete
Disciplines loaded
Structural EOR ✓ Mechanical sub ✓ Electrical sub ✓ Plumbing sub — placeholder only
Structural beam depths at room exit T1 resolved
Primary HVAC duct mains — exit routing T3 active
CHW / HHW pipe mains T3 held — awaiting duct main elevation

Loading phase — every discipline expected in this area submits their elements at the required level of development. The VDC manager tracks loading per discipline, monitors confidence levels, and runs the loading gate checklist. The gate has five criteria: all disciplines confirmed, minimum confidence met, no unverified T1 or T1A elements, gravity drainage path modeled, and VDC manager sign-off. Nothing in the loading phase is about solving — it is about confirming that the problem is fully visible.

Loading gate checklist
All disciplines confirmed Min confidence met per disc No unverified T1/T1A elements Gravity path modeled VDC manager sign-off

80% complete — one criterion remaining. Coordination is locked until the gate is passed.

Coordination phase — constraints are resolved in tier order. T1 and T1A constraints set the immovable boundaries. T3 constraints are resolved within those boundaries. T4 fills in what remains. The coordination phase is locked until the loading gate passes. If coordination has already started in an area where loading is incomplete, the system flags it as premature coordination — risk score is multiplied by 1.8 and all resolved constraints are marked provisional until loading completes and the gate is passed.

Premature coordination is the most expensive mistake in pre-construction. A team that coordinates 80% of an area's clashes before all disciplines have loaded will likely re-coordinate 60% of those solutions when the missing elements arrive. The loading gate exists to prevent this.

Resolve in tier order — always

Not all constraints are equal. Some are set by physics, regulation, or existing conditions and cannot move. Others are preferences that can adapt. Coordinating preferences before resolving the immovable constraints produces solutions that must be undone.

TierCategoryWho controls itRule
T0 Absolute fixed Regulatory / legal authority Cannot be changed under any circumstance. Municipal utility inverts, code-mandated clearances, property line setbacks. Establish these before the project starts.
T1 Structural primary Structural EOR Requires EOR approval and structural drawing revision to change. Beam depths, slab penetration locations, column positions. Resolve before any MEP routing.
T1A Gravity drainage spine Plumbing EOR / Civil EOR Physics-constrained. Every foot of horizontal run consumes irreversible vertical drop. The full slope path — roof drain to stack to underground invert — must be modeled at building scale before any ceiling coordination begins. Three audit checkpoints: shaft turn, mid-run, terminal invert.
T2 Fixed program Owner / PM Requires owner decision to change. Room dimensions, ceiling height commitments, program areas. Establish before primary MEP.
T3 Primary MEP distribution MEP subs and EORs Largest systems at full size — duct mains, pipe mains, bus duct, FP mains. Coordinate before secondary MEP. Duct main elevation sets everything below it.
T4+ Secondary MEP, architectural All trades Branch ductwork, branch piping, conduit home runs, devices, ceiling grid. Coordinate within the envelope established by T1 through T3.

Gravity drainage deserves its own tier — T1A — because it is not structural and it is not MEP. It is physics. A roof drain leader descending at 1/8 inch per foot over 140 feet of horizontal run consumes 17.5 inches of vertical drop before it reaches the stack. That number is fixed at the moment the stack location is set. Every duct, pipe, and conduit that runs parallel to that leader in the ceiling plenum must fit within what remains above the leader's invert. Getting the leader elevation wrong, or not modeling it at all before ceiling coordination begins, is the single most common cause of late-stage rework in commercial office buildings.

The coordination workflow

The tracker follows the natural sequence of a pre-construction coordination project. Each step builds on the one before. Skipping steps is visible in the data.

  1. Set up the project registry
    Go to the Registry tab first. Add every trade and consultant on the project with company name, contact person, and email. Define every building system that will be present — structural steel, HVAC mains, gravity drainage, electrical, FP, LV, existing-to-remain. Assign each system to its owning trade and set its default tier. Define the project milestones — loading gate, Tier 1 clash-free, coordination complete, fab release, IFC. This is done once and inherited by every area.
  2. Define coordination areas
    Go to Project view and create areas for every location where systems compete. Start with the highest-density, highest-consequence zones: the mechanical room threshold, primary shaft, below-grade connections, main corridor intersections. Each area gets a type, building level, density rating, criticality rating, sequence priority, and loading and coordination phase dates.
  3. Check which systems are present in each area
    Open each area's detail panel. Every system from the registry appears as a checklist. Check the ones present in this area. The system's owning trade is automatically added as a discipline requirement, and a placeholder constraint is created using the system's tier, gravity role, and coordination note as defaults. Systems not present in this area are shown but unchecked — they contribute nothing to scoring for this area.
  4. Run the loading phase
    For each area, track discipline loading. As each trade confirms their elements are submitted to the CDE at the required LOD, mark them loaded and update their confidence level — Unverified, Placeholder, Design intent, or Fab-ready. The loading gate checklist runs continuously. When all five criteria are satisfied, the VDC manager signs off the gate. Coordination is unlocked.
  5. Coordinate in tier order
    Work T1A constraints first — confirm invert elevations, stack locations, and slope paths. Then T1 structural constraints. Then T2 program commitments. Then T3 primary MEP. Hold T4 work until the tier above it is resolved. As constraints are worked through, move them from Open → Active → Resolved. The risk score for each area updates automatically based on what is open, what tier it is, and what confidence level has been reached.
  6. Run weekly coordination meetings in Meeting mode
    Switch to Meeting mode for the weekly session. Areas are presented sequentially in priority order on a full-screen display. Left panel shows every discipline's loading status. Right panel shows every constraint with its current status and a live clash count input. Run through each area, each trade confirms their status, clash counts are updated in real time.
  7. Log and commit the week
    In the Weekly tab, open a new week at the start of the coordination period. As updates come in — during the meeting or as follow-ups — log each one against the specific trade, area, and constraint. Status changes, confidence updates, loading confirmations, and gate sign-offs are all attributed and timestamped. At end of week, commit. The commit freezes a permanent snapshot, saves as a standalone week file, and generates a formatted email report listing every trade's commitments for distribution.
  8. Release for fabrication in sequence
    As areas complete coordination, constraints move to Resolved and the area coordination gate is passed. Fab release packages are logged as constraints at the T3 or T4 level with the sheet metal or piping sub as owner. The By Trade view shows each trade's completion status across all areas, so the VDC manager can confirm no trade is releasing for fabrication in an area where upstream constraints are still open.
01
Open week
VDC manager opens the week. Baseline snapshot is taken automatically.
02
Meeting + follow-ups
Trade updates logged during the meeting and via follow-up as the week progresses.
03
Commit
All updates in — VDC manager commits the week. Snapshot frozen. Week file saved.
04
Report out
Email generated showing each trade's commitments. Sent to full team.

Five views, one project file

All views read from and write to the same .vdcpt project file. Switching between them is switching context, not switching tools.

Tab 1
Project
The main coordination dashboard. Area list on the left, detail panel in the center, risk history and Gantt on the right. Select any area to see its loading and coordination phase status, discipline loading, constraint table, and system presence checklist.
Tab 2
Registry
Project-level definitions: trades and contacts, building systems with tier and gravity assignments, sign-off milestones. Defined once here, inherited by all areas. Edit any entry inline by clicking the row.
Tab 3
Weekly
The coordination commit cycle. Open weeks, log trade updates against specific constraints, compare progress to the prior week, commit to freeze the record, save standalone week files, and generate the distribution email.
Tab 4
By trade
Each trade's card shows their status across every area — loaded or not, coordination progress, resolved constraint count, and sequence violation flags. Filter to a single trade to see their full project picture in one view.
Tab 5
Meeting
Full-screen presentation mode. Areas displayed sequentially by priority. Left panel: discipline loading. Right panel: constraints with live clash count inputs. Designed to run on a shared screen during the weekly coordination session.
Integration
Navisworks
Export selection sets from Navisworks directly into the area definition dialog. Bounding volumes, element counts, and inferred system types flow in automatically. Live bridge available via local WebSocket server.

Files: The project saves as .vdcpt (VDC Phase Tracker) — a JSON file that does not conflict with any Windows application. Each committed week saves as a separate ProjectName-weekN-committed.vdcpt file. Both can be opened in any text editor, version-controlled in Git, and shared without any installation required. The tracker itself is a single HTML file that runs in any browser with no server.